Home » News & Blogs » Behind the Scenes at QM-2: Getting Ready to Test the World’s Largest Solid Rocket Motor
Bookmark and Share
Rocketology: NASA’s Space Launch System

Behind the Scenes at QM-2: Getting Ready to Test the World’s Largest Solid Rocket Motor

24 Jun 2016, 20:18 UTC
Behind the Scenes at QM-2: Getting Ready to Test the World’s Largest Solid Rocket Motor
(200 words excerpt, click title or image to see full post)

By Beverly Perry
For two monumental minutes on June 28, the Space Launch System (SLS) solid rocket boosters — the largest ever built for flight — will fire up in an amazing display of power as engineers verify their designs in the last full-scale test before SLS’s first flight in late 2018. Each piece of hardware that’s qualified and each major test — like this one, dubbed QM-2 — puts NASA one step closer on its Journey to Mars.
The smoke and fire may last only two minutes, but engineers at NASA’s Marshall Space Flight Center in Huntsville, Alabama and Orbital ATK in Promontory, Utah have been preparing weeks — even months — in advance for the static test of Qualification Motor 2 (QM-2). Here’s a behind-the-scenes look at what goes into getting ready to fire up the largest and most powerful solid rocket motor ever built for flight.
T (for test) minus weeks and months. In the months prior to the test, propellant-filled segments began arriving at Orbital ATK’s Test Bay T-97 after being cast in nearby facilities. Many of these segments are veterans of space shuttle flights. In fact, the various metal case segments that comprise the five-segment ...